Fees Calculator
Calculate estimated professional fees in real-time. Changes below are immediately reflected in the docked banner above. 1 Currency PoinT (CP) = UGX. 20,000.
Reference Information
Definitions as per the Architects Registration Act (Schedule 3).
Normal Services (Work Stages)
(A) Inception
Receiving an initial statement of requirements. Making preliminary layouts and estimates of development potential as allowed by statutory regulations. Outlining possible courses of action and advising on the need for quantity surveyor and other consultants. Agreeing with the client the basis for charging fees. Determining the brief in sufficient detail for subsequent stages to begin.
(B) Feasibility studies
Receiving amended statement of requirements, budget etc. making a detailed investigation into the restrictions imposed by relevant authorities and government statutes. Preparing sketches illustrating the overall form of the project. Advising on and applying for any modification or conversion of the site lease terms (if any). Such an appraisal may include an approximation of the cost of meeting the client’s requirements, a statement on the need for consultants, an outline timetable and suggested contract procedure or methodology.
(C) Outline Schematic Proposals
Analysing the client’s requirements and where necessary instructing the quantity surveyor and consultants. Preparing, describing and illustrating outline proposals, including an approximation of the cost of meeting them. Informing the client of any major decisions which are needed and receiving any amended instructions.
(D) Project Design
Preparing in collaboration with the quantity surveyor, and other consultants if appropriate, a scheme design consisting of drawings, and outline specification sufficient to indicate spatial arrangements, materials and appearance. Presenting a report on the project, the estimated cost and preliminary timetable for the project, for the client’s approval. Making submissions of these plans to any relevant statutory bodies.
(E) Contract Documents
Submitting plans prepared under section D above to the Local Authority and making any amendments necessary in order to obtain approval. Completing a detailed design and specifications as necessary, incorporating any design work done by other consultants, nominated subcontractors and suppliers. Preparing information necessary for the preparation of bills of quantities, if any, by the quantity surveyor, carrying out cost checks as necessary and preparing production drawings. Recommending suitable contractors for inclusion in a tender list and obtaining and advising on tenders and preparing and advising on the contract and the appointment of the contractor.
(F) Building construction
Obtaining the clients instruction regarding the acceptance of tenders. Obtaining consent to commence work from the Local Authority. Supplying information to the Contractor and arranging for him to take possession of the site and examining his programme. Making periodic visits to the site. Carrying out the statutory duties of the Architect as required under the provisions of the Conditions of engagement. Making periodic valuations of work done and materials on site and issuing certificates and other administrative duties under the contract. Accepting the building on behalf of the client, providing scale drawings showing the main lines of drainage and obtaining drawings of other services as executed, and giving initial guidance on maintenance. Preparing a schedule of defects at the end of the defects liability period and issuing a certificate of making good the defects. Preparing a priced Bill of Variations.
Classification of Buildings
Group I (High complexity)
Projects that are of high complexity, such as: Hotels, private residences, museums, religious buildings, judiciary buildings, special buildings, hospitals and theatres with stages, research and laboratories buildings, radio, TV and recording studios.
Group II (Normal complexity)
Projects of normal complexity, such as: Hostels, apartments, cinemas, special industrial buildings, schools, colleges and university buildings, office buildings, commercial buildings, leisure complexes, housing schemes, public housing, resorts, shopping centres, transport terminals and buildings for recreational purposes, public use and government services.
Group III (Simple natures)
Projects of simple natures, such as: tenements, go-downs, parking structures, industrial and warehouses or sheds.
Scale of Professional Charges (Table 1.1)
The following table outlines the percentage fees based on the Cost in Currency Points (CP). 1 CP = 20,000 UGX.
| Cost Range (CP) | Group I | Group II | Group III |
|---|---|---|---|
| Up to 42.5 CP | 7.00% | 5.75% | 4.75% |
| 42.5 to 85.0 CP | 6.50% | 5.50% | 4.50% |
| 85.0 to 425.0 CP | 6.00% | 5.00% | 4.25% |
| 425.0 to 680.0 CP | 5.50% | 4.75% | 4.00% |
| 680.0 to 850.0 CP | 5.25% | 4.50% | 3.75% |
| 850.0 to 1,275 CP | 4.75% | 4.00% | 3.50% |
| 1,275 to 1,700 CP | 4.25% | 3.75% | 3.25% |
| Over 1,700 CP | 4.00% | 3.50% | 3.00% |
Other Services (Part 4)
This part describes other services which may be provided by the architect. Unless otherwise stated, the fees for these services shall be on a time basis.
4.1 Signing of Agreement plans
Fees for checking and signing plans shall be **21.25 currency points** per set of two plans.
4.2 Arbitral Tribunals & Court Hearings
Fees for attending tribunals and Hearing Proceedings shall be as follows:
- First day: **85.0 currency points** (minimum)
- Second day onwards: **25.5 currency points** per hour.
Fees for attending court hearings shall be as follows:
- First day: **127.5 currency points** (minimum)
- Second day onwards: **25.5 currency points** per hour.
4.3 Demolition contracts
Fees for services in connection with demolition contracts or demolition or repair work shall be **85.0 currency points** (minimum) or **10% of the value of the demolition contract**, whichever is higher.
4.4 Town planning
Fees for town planning work shall be in accordance with the Professional charges of the Royal Town Planning Institute of UK, except that all layouts shall be charged on a time basis and all time charges shall be in accordance with Part 5 of these Conditions.
4.5 Quantity Surveying & Valuing
Fees for preparing bills of quantities, valuing works executed where no quantity surveyor is employed, valuation of properties and other surveying work not described elsewhere in these Conditions, shall be in accordance with the professional charges of the Institution of surveyors of Uganda.